Purpose : Control system for Control of BOILER 2*80 T/H
Description : Redundant CPU, Redunadant Power, Redundant Siemens S7-400 Control System with Remote Rack with PC-Panel as EWS/OWS ,Redundant Modbus/TCP Communication
Client: VENIRAN APADANA
10 – Sulfur Removal Unit in Ilam Petrochemical Complex
Purpose : DCS, ESD and F&G System of Sulfur Removal Unit in Ilam Petrochemical Complex .
Description : DCS, ESD and F&G System based on ABB 800xA
Client: ILPC
Consultant/Main Contractor: EIED
11 – WellHead South Azadegan HIPPS
Purpose : HIPPS Control System for South Azadegan WellHead .
Description : 58 HIPPS Logic Solver System based on HIMA H41Q
Client: NPC
Consultant/Main Contractor: Oil Design and Construction Company (ODCC)
12 – Engineering, Procurement, Construction and Installation of Wellhead Platform(S1), Submarine Cables and Pipelines Between S1 and Salman Complex
Purpose : Engineering, Procurement, Construction and Installation of Wellhead Platform(S1), Submarine Cables and Pipelines Between S1 and Salman Complex .
Description : S1 and Salman Complex Control System based on ABB 800xA
Client: IOOC
Consultant/Main Contractor: Asfalt Tous Company (ATC)
13 – Sarcheshmeh New Sulphuric Acid Plant
Purpose : Sarcheshmeh New Sulphuric Acid Plant Control System .
Description : Sarcheshmeh New Sulphuric Acid Plant Control System based on Siemens PCS7
Client: Fanavaran Parsian
Consultant/Main Contractor: Fanavaran Parsian
14 – SULFURIC ACID AND AMMONIUM SULFATE PRODUCTION PLANTS PROJECT
Purpose : Sulfuric Acid And Ammonium Sulfate Production Plants Project .
Description : SULFURIC ACID AND AMMONIUM SULFATE PRODUCTION PLANTS PROJECT based on Siemens PCS7 .
Client: Kimia Daran Novin Shomal Co.
Consultant/Main Contractor: Kimia Daran Novin Shomal Co.
15 – South Pars Gas Field Phase 14 Offshore Platform – Platform A and B
Purpose : South Pars Gas Field Phase 14 Offshore Platform – Platform A and B Control System .
Description : DCS, ESD and F&G Control System based on PCS7 and HIMA H51q .
Client: POGC.
Consultant/Main Contractor: ISOICO .
16 – South Pars Gas Field Phase 14 Offshore Platform – Platform C and D
Purpose : South Pars Gas Field Phase 14 Offshore Platform – Platform C and D .
Description : DCS, ESD and F&G Control System based on PCS7 .
Client: POGC.
Consultant/Main Contractor: ISOICO .
17 – Esfahan Refinery Water Treatment Plant
Purpose : Esfahan Refinery Water Treatment Plant Control System .
Description : DCS Control System based on PCS 7 .
Client: Esfahan Petrochemical Co .
Consultant/Main Contractor: Zolal Iran.
18 – Upgrading Control System of Sungun Copper Mine
Purpose : Upgrading Control System of Sungun Copper Mine .
Description : Upgrading control system from ABB Advant and Citect HMI (Based on Colibri) to ABB 800xA V6.1 .
Client: NICICO .
Consultant/Main Contractor: Zolal Iran.
19 – Gole Gohar Iron Ore Concentrate Plant
Purpose : Gole Gohar Iron Ore Concentrate Plant .
Description : Upgrading All DCS from ABB advant to ABB 800xA for 9 Substation, Stacker, Reclaimer and Stacker Reclaimer.